91ÃÛÌÒÊÓÆµ

91ÃÛÌÒÊÓÆµ

14 August 2025

Related Information

Mabey are Wiley in stoney Stanton

14 Sep 10 Mabey Hire Services has supplied a second temporary bridge to main contractor May Gurney as part of Network Rail’s upgrading of the Peterborough to Nuneaton freight line.

The 36-metre span, 50-tonne Mabey Universal steel panel bridge was lifted into place by a 500-tonne crane during an eight-hour operation on a recent Saturday night possession at Stoney Stanton near Leicester. 

The temporary bridge will maintain access to a Calor Gas depot for 13 weeks while the existing three-arch brick Wiles Bridge is demolished and rebuilt by May Gurney  as a single-span pre-cast concrete structure to enable larger container freight trains to run on the two lines underneath. 

The first Mabey installation was at Smiths Bridge earlier this year as part of a similar bridge upgrade on the same line. Mabey continued to work closely with May Gurney and were awarded the £88,000 contract for Wiles Bridge in July.

Mabey engineer John Thwaites said: “The site area at Wiles Bridge is quite tight. We were able to build the bridge in just three days in the compound but a traditional launch type installation was out of the question due to the restricted space.â€

The bridge was lifted into place in skeleton form and then decked in a single possession, minimising installation time and disruption to the line.

May Gurney site foreman Mark Little added: “It was a busy shift but we completed the works safely and ahead of time, and now the bridge works can commence in earnest.â€

The temporary bridge will be in place until late November when it will be removed during a further possession of the railway.

Got a story? Email news@theconstructionindex.co.uk

MPU
MPU

Click here to view latest construction news »